Feature #1991
Feature #1608: implement full appserver support (from 4GL clients only)
runtime support for appserver
Status:
Closed
Priority:
Normal
Assignee:
Target version:
Start date:
04/29/2013
Due date:
05/24/2013
% Done:
90%
Estimated time:
160.00 h
billable:
No
vendor_id:
GCD
Related issues
History
#1 Updated by Greg Shah about 11 years ago
- Target version set to Milestone 7
This task is just for time tracking. All history should be in the parent task #1608.
#2 Updated by Greg Shah about 11 years ago
- Due date set to 05/24/2013
- Start date set to 04/29/2013
- Estimated time changed from 128.00 to 160.00
- Assignee set to Constantin Asofiei
#3 Updated by Constantin Asofiei almost 11 years ago
- Status changed from New to WIP
#4 Updated by Greg Shah over 10 years ago
- % Done changed from 0 to 90
#5 Updated by Greg Shah over 10 years ago
- Status changed from WIP to Closed
#6 Updated by Greg Shah over 7 years ago
- Target version changed from Milestone 7 to Runtime Support for Server Features